When you synchronize Requirements or Stories between the
Atlas Hub and a testing tool,
Atlas can display the test results returned by your testing tool. In order to do this, your system administrator needs to use
Micro Focus Connect to connect the two systems.
See
Enabling Testing Tool Integration. After the systems are connected, you can use the following features to view test execution status:
- Requirement Tracking Tab
-
In the
Define perspective, open a Requirement and click the
Tracking tab. You will see the
Tests section.
There are two graphs:
- Latest Test Results
- This graph provides an aggregation of the statuses of all the Tests assigned to a
Requirement (and its children, if any), as they appear the last time they were executed.
N/A indicates Tests that are assigned but they have
never been executed (for example, a brand new test).
- Test Results Per Day
- Contains the following:
- The
Duration on the X-axis of the graph correlates to the duration supplied in the
Admin Tools. The number of tests in the Y-axis is that of the selected item, plus it's children.
- Click the legend (Passed/Failed/Not Run) at the top of the graph to turn each one on/off.
- The
Goto button takes you to the equivalent artifact in the integrated test tool.
- Hovering over an item gives you a tool tip with details.
- Test Integration in Tracking Dialog (Gantt)
- In the
Tracking perspective, open a plan in the Gantt.
- There is a
Tests column on the grid. Hover over the bars to view the details.
- In the
Change Overview section when in
Time Machine mode, there is a
Tests Count section in the overview. This displays the test count change over time